Processing major planning applications

We receive planning applications ranging from putting an extension on a house through to complex multi-million pound commercial developments.

Major applications are usually bigger and therefore have a larger impact across the district.

This can be wide-ranging from traffic and public rights of way to public amenity and climate change.

We have a team dedicated to dealing with major applications so we can deal with large planning proposals as quickly as possible.

We work with developers to ensure all major applications meet the policies and priorities identified in the North Somerset Local Plan.

Our major applications team provide a wide range of advice about large planning proposals and we strongly recommend developers contact the team before submitting an application.

If we receive a large planning application that was not discussed with our major applications team before submission, and which we consider to be an unacceptable proposal, it is likely to be refused within our 13 week approval target without an invitation to negotiate. 

A pre-application discussion will also help us to coordinate the advice we provide, for example whether an Environmental Impact Assessment is needed and if there any issues that require a legal agreement.

Where an application requires a legal agreement these must also be completed within our 13 week approval target. If this is not completed within the timescale we will refuse the application on the grounds that the proposal has failed to address the impacts caused by the development.

Before submitting a major planning application please read through our Statement of Community Involvement and speak to the relevant councillors and town and parish councils at an early stage.

For more information contact our Development Management team.